Building Permit/Final Inspection Status
Building Permit/Final Inspection Status
Name   [Green Valley LDS 3rd Ward]
Number   Grading-38383
Drawing of Record Submitted   1/03/08..revised 1/17/2008
Electronic Drawing of Record Submitted   1/03/08..revised 1/17/2008
Final Grading Report Submitted   1/10/2008
Date Scheduled   01/07/2008


BUILDING PERMIT RELEASE APPROVALS
Power  
Water  
Waste  
Engineering  
City Development Engineer  
Landscaping  


FINAL INSPECTION RELEASE APPROVALS
Power   1/08/2008 Approved per Dennis Wright 12/04/2008 Approved per Dennis Wright.. 1 year warranty
Water   1/8/2008 Corrections required Per Wayne M.. Need concrete around valve cans and arrows with pipe size cut in. Back flow need to have cert for Irr and Fire system. Paint Fire Hydrant down to the bottom of the concrete. Need to check locate wire. Need to lower Fie Hydrant need 8" of concrete around meter box and put rebar in the box. (Section 3.6.6.5 on Fire Hyd Spec) 1/15/2008 Approved per Wayne M 12/17/08 - 1 year warranty - approved per Daren Judd - Wire good.
Waste   1/14/2008 Approved per Glen Garland 12/04/2008 Approved per Glen Garland.. 1 yr warranty
Engineering   1/7/2008 Corrections required per Brandon Wright..Landscaping not complete,have not received Final Grading Report,show dentention basin on Drawing of Record,patch sidewalk and curb,lids on drain box & sidewalk,clean detention box and trough. 1/14/2008 Corrections required per Brandon Wright.. List not complete 1/18/2008 Approved per Brandon Wright 12/08/2008 Approved per Brandon Wright.. 1 year warranty
City Development Engineer   1/7/08 corrections required per Cathy H. Electronic DWG of record needs to show drainage improvements (location of holes in wall between church and homes, detention area and outlet structure etc). Per Ken B. Construction still in process. 1/14/08 corrections required per Ken B. Still installing landscape. 1/18/2008 Approved per Cathy H..Bond in place for landscaping 12/3/08 - 1 year warranty - just public roadway improvements - Approved per Ken B.
Landscaping   1/7/08 corrections required per Ken B. Construction still in process. 1/14/08 corrections required per Ken B. Still installing landscape. 1/18/2008 Approved per Cathy H.. Bond in place for landscaping 11/08/2008 Approved per Larry Shane.. 1 year warranty


General Comments