JUC STATUS
Current Status   Review Required
JUC 1st Review   9/27/11
JUC 2nd Review  
JUC 3rd Review  
JUC 4th Review  
JUC Approved  
JUC Comments:

9/27/11 JUC returned utility plans with comments from 1st review. Make corrections. When civil site plan construction drawings have been submitted for review and comments from JUC have been address, submit for 2nd JUC review.
 
CONSTRUCTION DRAWING STATUS
Current Status   Under Review
1st Review   10/14/11
2nd Review  
3rd Review  
4th Review  
Final Approval  
Construction Review Comments:

10/14/11 plans distributed for review. 10/20/11 received review from streets. 10/20/11 received review from planning. 12/6/11 plans returned for corrections. 7/26/12 received plans and distributed for review. 7/31/12 received review from streets.